Programme Of Works

Works for kitchen and/or bathroom replacement take 10-12 working days from start to completion including snagging.

The daily programme entails:

 

Day 1: Stripping wall tiles, floor coverings and wallpaper in kitchen and/or bathroom and removing kitchen units/worktops

Day 2: Remove Bathroom sanitary ware and change single sockets to double sockets in all rooms (if this option is chosen)
Rewiring kitchen and 1st fix plumbing

Day 3: Board and re-plaster kitchen and/or bathroom

Day 4: Install and fit new kitchen worktops and units and fit bathroom sanitary ware

Day 5: Wall Tiling to kitchen and/or bathroom and level floors

Day 6: Renew all electrics and 2nd fix electrical and light fittings

Day 7&8: Vinyl floor coverings to kitchen and/or bathroom

Day 9: 2nd Fix Plumbing

Day 10 & 11: Painting* Painting sometimes has to be delayed for an extra few days as it can only be done when plaster is completely dried out.